Placing Drawings are not Shop Drawings
By Dick Birley, President of Condor Rebar Consultants, Inc.
First published in Concrete International Magazine, December 2008
Requirements for early submittal can be detrimental
"Contractor will be required to have engineering such as submittals, shop
drawings, and samples submitted for approval within one hundred (100)
calendar days from written engineering notice to proceed."
Statements similar to this quote from the specifications
for a new stadium proposed several years ago appear
in many project specifications. In today's environment
of ever-shortening design and construction schedules,
it's understandable that specification writers feel it's
necessary to impose tight time constraints on the
delivery of shop drawings.
Although reinforcing bar placing drawings are often
assigned to the "shop drawings" category, it's important
to note that bar placing drawings are quite different from
the fabrication and installation drawings required for
other construction trades. In fact, the constraints
placed on the production of bar placing drawings may
make it impossible to comply with such a contract
demand in a manner that's productive for the detailer
or the contractor.
Gathering the information
There are many items on a construction project that
require shop drawings, including structural steel, precast
concrete, miscellaneous metal, mechanical and electrical
systems, and finish items such as doors and windows.
There is, however, a fundamental difference between
shop drawings for most items and reinforcing bar placing
drawings. Except for relatively minor embedded pieces in
concrete, most items detailed in shop drawings are
installed as self-contained systems or
as attachments to in-place systems.
In contrast, reinforcing steel is an
integral part of a much larger system
assembled during the concrete
placing process, and proper detailing
depends on how that process is
carried out.
There are two reasons why many
items need shop drawings prepared
as quickly as possible after the
project begins. Most importantly,
most items are manufactured
products with relatively long
delivery times. They must be
ordered as soon as possible to
ensure that they arrive on site at the
proper moment in the construction
process. The second reason is that
concrete cannot be placed until
final concrete dimensions are
determined. Although the architect
and engineer prepare the initial
concrete dimensions, these
dimensions are fine-tuned during
preparation of shop drawings for the
other items, including mechanical
and electrical equipment, windows
and doors, and concrete formwork,
required to suit the particular
requirements of the project.
Rapid, early preparation of
shop drawings is normally not
problematic for most of these other
items because they have relatively
little interdependence with each
other or casting concrete. For the
most part, the data needed for
production of these shop drawings
are not dependent on the work
performed by other trades.
A reinforcing bar placing
drawing is, however, an entirely
different matter.
First of all, reinforcing steel is
fabricated and installed as part of the
concrete placing process. The
builder cannot begin to cast concrete
until the final dimensions are known.
Likewise, reinforcing bar detailers
cannot complete their detailing until
they have the final dimensions.
Basically, detailers cannot complete
their placing drawings until most of
the other trades have completed
their drawings.
Furthermore, they cannot
complete placing drawings for many
parts of the structure, especially
slabs and walls, until concrete
contractors have completed their
formwork drawings and defined all
of the relevant construction joints.
In addition, there are often requestsfor-
information that will have to be
answered before placing drawings
for the areas in question can be
completed. Because of these issues,
detailers are often left with very little
lead time before the steel is needed.
As a result, they will have to know in
considerable detail the precise
construction sequence so they deal
with the most urgent items first.
The construction sequence is also
necessary so the detailer can
properly arrange for necessary
dowel projections from one placement
into the succeeding ones.
Fortunately, there is almost
always ample time for delivery of
reinforcing bars, even if the placing
drawings are prepared and approved
only a couple of weeks before the
steel is needed in the field. Because
reinforcing bars are readily stockpiled
and ready for almost immediate
cutting and bending, production can
be quite rapid. For all of these
reasons, there is no compelling
need to prepare placing drawings
"within one hundred (100) calendar
days from written engineering notice
to proceed."
To complete their jobs properly,
detailers must have at hand a great
deal of data that often doesn't come
until it becomes critical—in other
words, until the lead time is gone and
they are in danger of not completing
their work in time for a placement.
This is why the reinforcing bar
detailers always seem to be behind
schedule—they are the last people to
get all the information they need to
complete their jobs. Those that don't
understand this may assume that
detailers are submitting their placing
drawings at the last moment due to poor planning or
incompetence, but that's simply not a fair assumption.
What's best for the project?
If the reinforcing steel for a project is detailed within
100 days after notice to proceed, or simply ahead of the
availability of proper data, it's almost certain that a great
deal of the detailing will have to be revised. A detailer
details on the basis of a unit price per ton of steel that is
included in the bid price. Revising detailing is usually
done at an hourly rate. The cost for redetailing in such a
situation can be enormous and can be as much or more
than the cost of the original detailing. This is a significant
and needless cost to be passed on to the client or the
client's client.
Awareness of these issues makes clear that the
request for detailing to be completed far ahead of the
required schedule is unreasonable. The issue at hand
is to try to get all the necessary information to the
reinforcing bar detailers as quickly as possible so they
can keep ahead of construction. Reinforcing bar
placing drawings are simply not the same as other
shop drawings, and care should be taken to treat them
as distinct and separate.
Continue to The Tolerance Cloud -->
|